noCV
BMONO-106 · Build the planner

Make cache keys include generator versions and relevant environment

Practice briefBugAdvanced

Generated client code changed after a tool upgrade while the cache reused an old successful result.

Focused work estimate
3h 30m + prerequisites
Priority in the scenario
High
Engineering practice
Caching · Reproducibility

Estimated field mix

  • Developer tooling70%
  • Storage systems30%

Field percentages are editorial estimates of the ticket's engineering focus. They total 100%; they are not measured time, proficiency scores, or ownership evidence.

Your next step

Review it, then add it to your workspace.

The board opens an editable draft; nothing is saved until you confirm it. Sign-in and workspace permissions apply, and Demo boards remain ephemeral.

Project context

A fictional internal tools team maintains eighteen packages. Engineers currently run everything because the affected-package script occasionally misses downstream consumers.

Setup prerequisites

  • Create a local six-package fixture with a dependency cycle, shared compiler configuration, and two example changes.

Preceding work

Complete these dependencies, or supply their agreed outputs before taking this ticket.

Acceptance criteria

  • Hash declared inputs using stable ordering.
  • Include generator version and allowlisted environment names.
  • Exclude secrets and unrelated environment values from key material.

Implementation constraints

  • A cache hit must never authorize skipping an undeclared dependency.

Verification to include

  • Change each declared input and observe key changes.
  • Verify secret values are absent from keys and diagnostic output.

Deliverables

  • Cache-key contract and regression checks.

Rollout and recovery

Invalidate old keys on adoption; revert to uncached commands if key provenance is missing.

Value of the work

For the engineer: Practice graph analysis, reproducible commands, and safe developer-tool failure modes.

For the team: Produce an inspectable CI selection plan that avoids unnecessary work without silently skipping consumers.

Evidence boundaries

Outcome Evidence: Tests, patches, and runbooks are requested deliverables. They become Outcome Evidence only through a qualified Mission and immutable Evidence IDs.

Ownership Evidence: Independent adaptation must be observed under a declared verification policy and cite immutable Evidence IDs. Completing a planning ticket establishes no Ownership Evidence.